Aventis Pharmaceutical Factory and Extension (Sanovi - Aventis) - Phase I & II

Aventis Pharmaceutical Factory ¨C Phase I & II
¨C D&B including Validation for Phase I and GC for Phase II

 
The pharmaceutical facilities (Phase I) consist of a main workshop building, guardhouse, pump house, underground wastewater treatment plant, alcohol store and bicycle shelter. The gross floor area is 8,000 m2.
The factory in compliance to GMP and FDA requirements. Special safety standards due to use of flammable powders.
Clean room:

Class 10,000 and Class 100,000. Internal flat aluminium windows are used and necessary sealing treatment was carried out. Hoermann steel door system was chosen with similar treatment to the bottom corners and frames. To make sure of the sealing function in the clean area works and to keep the balance of the air pressure, semi-quick-doors are installed, this also saves energy.
Phase II extension works includes five main zones for production, cold storage, and offices with gross floor area of 15,000 m2. The extension also includes related external works.

 

Back

Head Office£º
Unit 1080 Beijing Sunflower Tower 37 Maizidian Street Zhaoyang District Beijing 100125 P.R. of China ¡¡
Tel£º+86 10 8527 5116¡¡¡¡ Fax£º+86 10 8527 5123
E-mail£ºalpine@amc-constr.com.cn111
ZECH GROUP LINK£º
Copyright © ALPINE Mayreder Construction Co., Ltd. (AMCC)¡¡   Imprint |¡¡Privacy